Refinery Saves Upwards of $250,000 on Critical Assets

After years of limited maintenance history, a refinery was in need of a full-system flush and reservoir clean-out to prevent potential system failures and downtime.

Project Details
Type of System
Screw Compressor
Type of Lubricant
CITGO Pacemaker T-32
Total Project Time
4 Days
Result
Successful completion of HVOF

Sector:

Petrochemical

Location:

Louisiana

Service:

Oil Sampling and Oil Flush
The
Challenge
A refinery requested to have their system flushed due to lack of maintenance history. The system had been out of service for many years, so this was a proactive measure.
The
Solution
Due to the lack of maintenance, Breaux Energy Services gave two recommendations. The refinery moved forward with a high velocity oil flush for their entire lube oil system, as well as a plumbing and reservoir clean out. Once start-up occurred, BES also performed an oil sampling to capture varnish potential and water content.
The
Result
The result was a successful, on-time, and on-budget project that saved the refinery up to $250,000 in critical component replacement costs.

“Breaux performed several high velocity flushes on major rotating equipment within our refinery amongst other lube oil console flushes. Their employees were always on time, worked diligently, communicated well with our plant personnel, and above all, performed their work safely. Breaux will continue to be our go-to for all of our filtration and lube oil service needs within our refinery. We appreciate the partnership we have with Breaux and the excellent services they provide every day.”  —Project Lead, Rotating Equipment Engineer.
BES successfully completed the project on-time and within the budget parameters provided by customer.